we as regional workers always review in the field of waterways and rivers .. what we review is a location that has not been worked on, we usually call it the zero point in the work or the initial drawing of the work.
when we start working we still use heavy equipment or excavators ... we dig excavations according to local requests with speck prioritized. We always take care of the health of the workers.
when we finish the work according to the specifications of the excavation face area of 350 centimeters, the bottom area is 270 centimeters and the depth of the excavation is 250 centimeters, if everything is suitable then the water canal is 1000 meters or 6785 cubic meters.We created this channel based on the community's submissions for the common interest in agriculture, plantations and overcoming the flood which always disturbs the residents, congratulations there is a waste channel, the community is very lucky.
Leave working on irrigation canals to:
Read more #aceh posts
Best Posts From Asr13l
We have not curated any of asr13l's posts yet. But you can encourage our curation team to review posts by visiting them regularly and by referring other readers. Because we give priority to frequently read content.
More Posts From Asr13l
- simple business
- edged water waves
- world dollar nest hunter
- beach flower
- Flowers that are considered by Indonesian people to contain mystical
- how far to go to hometown
- My introduction strikes the beauty of the beach and foodies bee sarang
- the beauty of nature at night
- working on irrigation canals
- The power of love